CH 17 Trail Project

Project Details

  • Construction Year: 2021-2022
  • Community Served: Shakopee
  • Corridor: CH 17
  • Project Lead: Scott County
  • Contractor: Kraemer North America, LLC.
  • Construction Start: September 2021
  • Status: completed 2023

Description

A trail segment gap and a pedestrian/bike overpass of TH 169 has been constructed along the west side of CH 17 from CH 16 to the NW ramp of TH 169 in the city of Shakopee. 

Purpose & Justification

Scott County was awarded federal funding to construct a section of trail along CH 17. The pedestrian/bike overpass closes a trail gap and provides a facility that crosses TH 169 and gives a direct pedestrian link to the Marschall Road Transit Center. 

Project Schedule

  • Preliminary Design: Fall 2019
  • Final Design: Fall 2020
  • Right-of-Way/Easement Acquisition: Fall 2019-Fall 2020
  • Construction: Fall 2021- Fall 2022