Details
- Construction Year: 2021
- Community: Helena Township
- Corridor Served: CH 2 & CH 15
- Project Lead: Scott County
- Contractor: Heselton Construction, LLC.
- Construction Start Date: June 21, 2021
Description
Improving the safety and operations of the intersection at County Highway 2 and 15 in Helena Township. This project will reconstruct the intersection as a single lane roundabout and is programmed for construction in 2021.
Purpose & Justification
Safety and operational deficiencies will be best addressed with the reconstruction of the intersection as a roundabout.
Project Schedule
- Preliminary Design: Summer 2019
- Final Design: Fall 2020
- Right-of-Way/Easement Acquisition: Fall 2019 to Winter 2020
- Construction: Spring 2021