None. Project is complete.
Project Updates:
June 30, 2020: Storm sewer work has begun and will continue for the next two weeks, followed by construction of the roundabout and road work.
July 10, 2020: Crew wrapping up storm sewer installation and will be moving on to grading work.
August 5, 2020: Concrete is poured and crews are working on pedestrian ramps and trails. Paving is scheduled for next week. Road is anticipated to reopen to traffic August 25, 2020.
August 25, 2020: Intersection is reopened to the public!
September 3, 2020: Striping planned next week for the roundabout after Labor Day.