CH 21/TH 13 Reconstruction

  • Construction Year: 2019
  • Community: City of Prior Lake
  • Corridor Served: CH 21
  • Project Lead: Scott County
  • Contractor: S.M. Hentges & Sons, Inc.
  • Anticipated Construction Completion: July 2020

Project Schedule/Progress:


The 13-21 roundabout will begin construction on March 23, 2020.

Concrete curb at the 21/13 roundabout started this week May 11 and is anticipated to be completed Saturday, May 16, 2020. Paving prep and the first two lifts of asphalt are scheduled to begin at the end of next week, May 22, 2020 and continue into June.
 
Landscaping, flatwork concrete, decorative concrete and street lighting has been ongoing at West Avenue and nearing completion up to Arcadia.

Traffic Control:

Mon, March 23, 2020 Eastbound lane closure on CR 21 from TH 13 to Franklin Trail.
Mon, March 30, 2020 Full intersection closure will begin.
Tues, May 26, 2020 Main Ave and CR 21 will have a full closure for approximately 10 days, weather permitting, to install curb and medians at the intersection. See map (pdf).
      

Project Details


Scott County, in coordination with the City of Prior Lake and the Minnesota Department of Transportation, is planning intersection improvements on County Highway (CH) 21 and State Highway (TH) 13 in downtown Prior Lake.  This intersection was identified as needing improvement due primarily to mobility concerns, but also in regard to traffic safety concerns associated with the existing and forecasted traffic.

The project will evaluate potential improvements to intersections in close proximity to the CH 21/TH 13 intersection, in particular CH 21 and Main Avenue.  It will also take into consideration traffic impacts on surrounding streets, including impacts on pedestrian safety and accessibility.
 
The focus of this effort will be on downtown Prior Lake, with a corridor visioning exercise completed for the longer segment of CH 21 from CH 82/154th Street to Franklin Trail.  The Corridor Visioning Study will help to identify how the intersection reconstruction project can holistically fit into the future vision of the corridor and its surroundings.

Project Goals


  • Enhance vehicle mobility on major transportation corridors
  • Safely accommodate all users along the major transportation corridors
  • Provide a comprehensive network for non-motorized transportation that is compatible with the major transportation corridors
  • Provide infrastructure improvements compatible with the natural and human environment
  • Develop a financially responsible infrastructure implementation plan
  • Preserve and enrich the character of downtown Prior Lake

For More Detailed Information


Watch a short video on the intersection reconstruction project here.  
  


Go to the project website at www.movingforward13-21.com or visit the project's Facebook page here

Construction Drone Footage

Drone Progress Photos May 20, 2020

Project Location

CH21 TH 13 project area